Bolnisi Municipal Landfill Has Been Rehabilitated

Home/News, Uncategorized/Bolnisi Municipal Landfill Has Been Rehabilitated

Bolnisi Municipal Landfill Has Been Rehabilitated

Bolnisi municipal landfill rehabilitation works are accomplished. Giorgi Shukhoshvili, the director of Ltd. “Solid Waste Management Company of Georgia” and Gogi Meshveliani, the Head of Bolnisi Municipality, together with the local self-government unit representatives visited the rehabilitated municipal landfill and checked the carried out works.

Bolnisi municipal landfill operates since the year of 1975. The total area of the landfill comprises 50316.34m² and about 15.6m³ household waste is being disposed daily on the landfill territory from Bolnisi municipality and its nearby villages.

Bolnisi municipal landfill was transferred to the possession of Ltd. “Solid Waste Management Company of Georgia” on July 10, 2013. At the time, the state of the landfill was horrible: waste was being disposed unorganized at the landfill perimeter, operational standards have been neglected, no ecological and sanitary norms were observed, and control and sanitary supervision of the landfill perimeter was not followed. The landfill territory was not fenced, thus, the nearby population as well as domestic animals could easily reach the disposed waste on the landfill territory, which raised a risk of infection contamination among the poultry, cattle and municipality population. As a result of all these, operation of the landfill was dangerous for the environment and nearby population.

In coordination with the Ministry of Regional Development and Infrastructure of Georgia, Ltd. “Solid Waste management Company of Georgia” implemented Bolnisi municipal landfill rehabilitation project. Within the project framework the following works were carried out: the landfill territory was fenced, inner roads and drainage system were arranged, disposed waste was covered with an isolation layer, special waste cells were prearranged for further utilization, a watch-box, and equipment hood, firefighting shield, landfill renders, and no trespassing-signs were set, the landfill perimeter was fully electrified (solar photo-electronic system was set), the landfill was provided with needs-based equipment and human resources.

The rehabilitation project cost amounted to 317.600 Georgian Lari. The project was financed from the state budget and was implemented by the State tender-winner company – Ltd. “Lava.” Project employed 8 persons, out of which 6 were locals. The project works were accomplished on May 19.

At the renovated landfill, waste treatment and disposal will be determined in accordance with the existing standards and thus, the dangerous influences upon the environment will be reduced and local population safety and living conditions will be improved.